HINTON BRIDGE ON GRS ABUTMENTS
Services
- Engineering & Construction
Customer
West Fraser - Hinton FP
Project Date
2015
Location
Hinton-EdsonLandmark was contracted by Hinton Wood Products to replace a culvert at crossing 185 with a steel girder bridge on Geosynthetic Reinforced Soil (GRS) abutments. The process involved damming the existing flow using steel sheet pile and diverting the streamflow during construction of the abutments. A winch truck and excavator were used to launch the bridge.
Another successful project done in collaboration with Terratech Consulting Ltd.